The words on this site, defined.

Each term as the site uses it, with its source where a fact backs it.

01 / Terms

14 terms: the programme first, then information management.

  1. 01

    DCMA 14-point assessment

    14 checks on the health of a programme, from the Defense Contract Management Agency's schedule metrics. Most checks carry a threshold; a programme passes or fails each one.

    Source: DCMA, EVMS Program Analysis Pamphlet, PAM 200.1
  2. 02

    Data date

    The date a programme update is measured at. Work before it is recorded as it happened; work after it is forecast.

    Source: US Government Accountability Office, Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G (p. 122)
  3. 03

    Float

    The time an activity can slip before it delays completion. Negative float means the programme is forecast to finish after its required date.

    Source: Society of Construction Law, Delay and Disruption Protocol, 2nd edition (Appendix A, total float)
  4. 04

    FragnetSub-network

    The few activities added to a programme to model one delay event, so its effect on completion can be shown.

    Source: Society of Construction Law, Delay and Disruption Protocol, 2nd edition (Part B guidance, paragraph 4.3, p. 24)
  5. 05

    EOTExtension of time

    More time to complete under the contract, asked for or granted against a delay event.

    Source: Society of Construction Law, Delay and Disruption Protocol, 2nd edition (Appendix A, extension of time)
  6. 06

    DAABDispute avoidance and adjudication board

    A standing board that helps the parties avoid disputes and decides the ones that arise. Abu Dhabi's revised government contract, the ADGCC, includes one on government capital projects.

    Source: Abu Dhabi Media Office, ADPIC
  7. 07

    Primavera P6

    Oracle's planning and scheduling software, common on large projects. An .xer file is a programme exported from it.

    Source: Oracle, Primavera P6 Professional documentation, Importing and exporting: import/export file formats (doc set F25600_01)
  8. 08

    ISO 19650

    The international standards for managing information about a built asset over its whole life, using building information modelling.

    Source: ISO, ISO 19650-1:2018 Information management using building information modelling, Part 1: Concepts and principles, Edition 1 (abstract)
  9. 09

    BIMBuilding information modelling

  10. 10

    CDECommon data environment

    The agreed place a project's information lives. Each file, or container, moves through 4 states: work in progress, shared, published, archive.

    Source: UK BIM Framework, Guidance Part C
  11. 11

    OIROrganisational information requirements

  12. 12

    AIRAsset information requirements

  13. 13

    EIRExchange information requirements

  14. 14

    BEPBIM execution plan

    The delivery team's plan for how it will manage information on an appointment, in response to the exchange information requirements.

    Source: UK BIM Alliance, CDBB and BSI, Information management according to BS EN ISO 19650, Guidance Part 1: Concepts, 1st edition (Annex C.1), hosted by CDBB; later editions exist

Start here

Start with a health check.

  1. 01

    You send

    a Primavera P6 export (.xer) and your notice, variation and extension of time registers.

  2. 02

    We run

    the 14 DCMA checks, then notices, variations and extensions of time.

  3. 03

    You get back

    the findings ranked, each with its fix.